New Town Hall timeline changes

The timescales for the regeneration of the eastern end of The Boulevard – including a new Town Hall – have changed.

Demolition of the eastern part of the Town Hall has been moved back to October 2019. This change to the work programme has been made to reduce financial risk and to take account of delays due to investigations into potential listing.

This provides the council with the opportunity to bring the Council Chamber and Civic Hall back into use until June/July 2019, when decommissioning will commence.

Publish Date: 
Friday, September 14, 2018 - 11:45

County Mall cycle path takes shape

Work on upgrading a pathway at the south side of Memorial Gardens, to improve cycle links around the town centre, has started.

The pathway connects County Mall and Memorial Gardens to the toucan crossing on College Road and is currently only wide enough to accommodate pedestrians. The proposed scheme will mean that the pathway will be widened to allow both pedestrians and cyclists continuous, safe access to and from the town centre.

Publish Date: 
Wednesday, March 14, 2018 - 10:00

Town Centre Signage: thank you for your feedback

Crawley residents were invited to share their feedback on proposals for the new town centre signage and specifically the icons and images that will appear on the signs. The designs follow the town's new place branding which was created after a period of consultation with key stakeholders, the Town Centre Partnership, together with Crawley Borough Council, in February 2017.

The branding celebrates Crawley’s new town history while adding a colourful and modern twist with the use of iconography reflecting landmarks, places of interest, shopping and eating etc.

Publish Date: 
Thursday, February 22, 2018 - 09:30

Have your say on Crawley’s new place branding

Residents are being asked for their input into Crawley’s new place branding; a unique, visual brand owned by all stakeholders to help promote a sense of place and character in the town centre.

The Town Centre Partnership, together with Crawley Borough Council, commissioned the creation and design of the brand in 2016 which was agreed in February 2017. It’s currently being implemented following a great deal of research and consultation and is designed to inspire and attract residents, visitors and businesses, offering visual identification and place making.

Publish Date: 
Wednesday, January 17, 2018 - 11:45

Updated Town Centre Regeneration Programme- open for comments

The Town Centre Regeneration Programme outlines ambitious plans to regenerate the area which has recently been rated the 23rd hottest retail opportunity and third best premium retail opportunity in the UK by researchers, CACI.

Following significant progress since the programme was first launched in Spring 2016, we have recently updated it and are keen to hear your views.

Publish Date: 
Thursday, December 14, 2017 - 14:00

The bandstand is coming back!

The town’s Victorian bandstand is now a step closer to being restored and relocated to the Memorial Gardens.

Crawley Borough Council has been working with specialist Leander Architecture to refurbish and restore the bandstand after it was moved from Queens Square to make way for the regeneration works in 2016. The bandstand was placed in storage and is now being returned to its former beauty, at Leander’s workshop in Derbyshire, before being installed in the north-west corner of the Memorial Gardens.

Publish Date: 
Wednesday, November 22, 2017 - 09:15

Queensway & The Pavement regeneration plans submitted

Plans to regenerate Queensway, Kingsgate and The Pavement, continuing the high quality improvements in Queens Square, have been submitted.

The proposals, which mark the second phase of town centre regeneration, run from the eastern edge of Queens Square along Queensway to the College Road junction, including part of the boundary to Memorial Gardens, and the length of The Pavement.

The plans, which would significantly improve the three main connector streets and it’s hoped would act as a catalyst for wider regeneration and investment, provide:

Publish Date: 
Tuesday, November 7, 2017 - 15:30

Major Local Growth Fund investment for Crawley

We are delighted to announce that on 21st September 2017, a substantial Local Growth Fund investment of £14.64 million has been confirmed by Coast to Capital Local Enterprise Company for this significant regeneration programme in Crawley.

Publish Date: 
Saturday, September 23, 2017 - 19:15

Queens Square update - 11 July 2017

Over the last month, Queens Square has really started to take shape with six of the eight granite planters being installed and four Ginkgo Biloba trees being planted. The final planters and three more trees will be installed over the next few weeks. Paving has been laid across almost all of the western side of the square with new colours of white, red and black granite used around the fountain area, according to the approved design.

Publish Date: 
Tuesday, July 11, 2017 - 09:15

Have your say on major town centre redevelopment

Residents are being asked for their views on plans for a major redevelopment in the town centre.

The proposals for land at the eastern end of The Boulevard will see the current Town Hall replaced with a new Town Hall with grade A commercial offices for rent to help fund local services, a new public square and public realm improvements.

Publish Date: 
Monday, July 3, 2017 - 10:45

Pages

Subscribe to RSS - town centre